Rehabilitate
Runway 14/32

A substantial pavement area of Runway 14/32, mainly the load bearing 50 foot keel section, is in poor and failed condition and in need of rehabilitation. Rehabilitation of Runway 14/32 will eliminate runway FOD and enhance safety and bring the runway up to standards.

Jose Luis Flores

Airport Director

5210 Bob Bullock Loop

Laredo, Texas 78043

Phone: (956) 795-2000

Fax: (956) 795-2572

jlflores@ci.laredo.tx.us

Runway 14/32:

Engineering plans and specifications are being prepared and are scheduled to bid by May or June 2007 ready to bid.

 

The City of Laredo requests an AIP Discretionary Grant during FY 2007 in the estimated amount of $6.0 million to rehabilitate Runway 14/32, to include electrical upgrades.